01
Release the room against approved information
Confirm that the latest approved plans, elevations, material schedule, interfaces, and room numbers are available to the installation team. Identify variations that have not yet been incorporated.
The room-release record should state whether construction dimensions and service positions were rechecked and which incomplete items are accepted with a defined action owner.
02
Verify delivery and handling
Check vehicle access, unloading restrictions, dock or ground conditions, door and lift dimensions, turning areas, floor loading, protection, and any lifting equipment or permits.
Match package dimensions and weights to the route. Establish secure temporary storage and a package sequence that avoids opening or moving every item to reach the next room.
- Unloading and vehicle access
- Horizontal and vertical transport
- Opening and turning dimensions
- Temporary storage and package sequence
03
Confirm the installation environment
Review floors, walls, ceilings, lighting, ventilation, temperature and humidity conditions where relevant, site power, cleanliness, and protection from water or ongoing high-risk work.
Other trades should not block furniture positions or damage installed surfaces. Agree on floor and wall protection, dust control, waste removal, daily cleaning, and custody of completed areas.
04
Coordinate services, safety, and acceptance
Verify service locations and isolation status before drilling or cutting. Confirm which party performs final connections, sealing, testing, commissioning, and making good.
Set installation inspections and sign-off points for concealed work, positioning, levelling, fixing, joints, doors, drawers, finishes, services, cleaning, and outstanding items.